Contract Agreement Amount

Rs. 5,42,30,634

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Construction of Prestressed RCC bridge over Belauti Nadi, Parwaha Station dekhi Bharariya Border ma parne, Dhanusha

Office: डिभिजन सडक कार्यालय, धनुषा (17)

Fiscal Year: 071-72

0.00%

Contract Date: 16-Jul-15

Start Date: 16-Jul-15

Completion Date: 30-Sep-2020 (EOT Done)

Project Description

No description available.