Contract Agreement Amount
Rs. 51,04,671
Physical Progress
0.00%
Financial Progress
25.21%
Remaining Payment
Rs. 74
Specific Maintenance (Drain cover and culvert) Works along Hetauda-Lothar Section of MRM
Office: डिभिजन सडक कार्यालय, मकवानपुर (19)
Fiscal Year: 077-78
Contract Date: 6-Apr-21
Start Date: 6-Apr-21
Completion Date: 09-Jul-2021 (EOT Not Done)
Project Description
No description available.