Contract Agreement Amount

Rs. 12,15,09,327

Physical Progress

26.00%

Financial Progress

25.00%

Remaining Payment

Rs. 75

Periodic maintenance of “ Siddhartha Highway(H10), Galyang-Kubhinde Section(Ch :100+000 to 164+710 Km); birauta-Prithivichowk Section( ch: 179+320 to 181+220 Km), and Pokhara Baglung Road, Bindabasini Yamdi Section(ch:4+720 to 6+720 Km )”.

Office: मध्यपच्चिमाञ्चल क्षेत्रिय सडक निर्देशनालय,सुर्खेत (10)

Fiscal Year:

26.00%

Contract Date: 8-Feb-22

Start Date: 8-Feb-22

Completion Date: 08-Feb-2023 (EOT Not Done)

Project Description

No description available.