Contract Agreement Amount

Rs. 12,70,16,595

Physical Progress

35.00%

Financial Progress

24.94%

Remaining Payment

Rs. 75

Improvement of Araniko Highway Hanuman Mandir-Pachkhal Bazzar- Ziro Kilo Road ( CH:43+200 to 45+000

Office: सडक डिभिजन, डोटी (35)

Fiscal Year: 078-79

35.00%

Contract Date: 15-Nov-22

Start Date: 15-Nov-22

Completion Date: 10-May-2024 (EOT Not Done)

Project Description

No description available.