Contract Agreement Amount

Rs. 71,44,240

Physical Progress

25.00%

Financial Progress

24.87%

Remaining Payment

Rs. 75

M/S Darshan Nirman Sewa

Office: सडक डिभिजन, कपिलवस्तु (29)

Fiscal Year: 079-80

25.00%

Contract Date: 14-Mar-23

Start Date: 14-Mar-23

Completion Date: 05-Jul-2023 (EOT Not Done)

Project Description

No description available.