Contract Agreement Amount
Rs. 1,28,43,70,871
Physical Progress
16.00%
Financial Progress
24.29%
Remaining Payment
Rs. 75
Upgrading of Galchi Trishuli Mailung Road to Dedicated Double Lane Standard (Chainage 46+000 to 64+814 )
Office: गल्छी त्रिशुली मैलुङ्ग स्याफ्रुवेशी रसुवागढी सडक योजना, विदुर नुवाकोट (83)
Fiscal Year: 076-77
Contract Date: 16-Jul-20
Start Date: 30-Jul-20
Completion Date: 28-Jan-2023 (EOT Not Done)