Contract Agreement Amount
Rs. 1,41,81,425
Physical Progress
20.00%
Financial Progress
23.93%
Remaining Payment
Rs. 76
Emergency maintenance works at Khadichaur- Mude section NH23-009 ( Chainage 5+900 to 21+400), Sindhupalchowk
Office: यान्त्रिक कार्यालय, चितवन (46)
Fiscal Year: 079-80
Contract Date: 23-May-23
Start Date: 23-May-23
Completion Date: 17-Aug-2023 (EOT Not Done)
Project Description
No description available.