Contract Agreement Amount

Rs. 1,41,81,425

Physical Progress

20.00%

Financial Progress

23.93%

Remaining Payment

Rs. 76

Emergency maintenance works at Khadichaur- Mude section NH23-009 ( Chainage 5+900 to 21+400), Sindhupalchowk

Office: यान्त्रिक कार्यालय, चितवन (46)

Fiscal Year: 079-80

20.00%

Contract Date: 23-May-23

Start Date: 23-May-23

Completion Date: 17-Aug-2023 (EOT Not Done)

Project Description

No description available.