Contract Agreement Amount

Rs. 80,39,040

Physical Progress

10.00%

Financial Progress

23.39%

Remaining Payment

Rs. 76

Highway Upgrading and Rehabilitation Works along Shitalpati Khalanga Kupinde Baluwasangrahi Road in Salyan District.

Office: वनेपा सिन्धुली वर्दिवास सडक योजना, काठमाण्डौ (78)

Fiscal Year: 078-79

10.00%

Contract Date: 18-Sep-22

Start Date: 18-Sep-22

Completion Date: 19-Mar-2023 (EOT Not Done)

Project Description

No description available.