Contract Agreement Amount

Rs. 46,93,790

Physical Progress

0.00%

Financial Progress

23.33%

Remaining Payment

Rs. 76

Maryadpur Sitalpur Mewa Sadak, Rautahat

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 076-77

0.00%

Contract Date: 11-Dec-19

Start Date: 11-Dec-19

Completion Date: 29-Dec-2020 (EOT Done)

Project Description

No description available.