Contract Agreement Amount
Rs. 5,30,66,594
Physical Progress
44.62%
Financial Progress
23.11%
Remaining Payment
Rs. 76
Construction of Jallad khola multicell box culvert along janakpur yadukoha road
Office: डिभिजन सडक कार्यालय, धनुषा (17)
Fiscal Year: 078-79
Contract Date: 1-Jul-22
Start Date: 1-Jul-22
Completion Date: 31-Jan-2024 (EOT Done)
Project Description
No description available.