Contract Agreement Amount
Rs. 25,35,39,823
Physical Progress
25.00%
Financial Progress
23.11%
Remaining Payment
Rs. 76
Roadway upgrading works including Roadyway Excavation works, Structural works and Pavement works on Kunaghat (Bichaour) Bhumlichowk Fulanggiri Gaudabhanjyang Road (Saam Ghaderi to Fullanggiri Section)
Office: सडक डिभिजन, तनहुं (25)
Fiscal Year: 078-79
Contract Date: 7-Jul-22
Start Date: 7-Jul-22
Completion Date: 13-Jul-2024 (EOT Not Done)
Project Description
No description available.