Contract Agreement Amount

Rs. 24,96,99,425

Physical Progress

27.00%

Financial Progress

22.91%

Remaining Payment

Rs. 77

Construction of Project Directorate Office Building with necessary accessories at Bishalnagar, Kathmandu

Office: Unknown (1)

Fiscal Year: 078-79

27.00%

Contract Date: 24-Jan-22

Start Date: 24-Jan-22

Completion Date: 11-Apr-2024 (EOT Not Done)

Project Description

No description available.