Contract Agreement Amount
Rs. 26,89,040
Physical Progress
100.00%
Financial Progress
22.15%
Remaining Payment
Rs. 77
Improvement of Parasan India Border-Tribhuwanbasti-Vakunda-Chandev-Naya Basti Road, Kanchanpur
Office: सडक डिभिजन, कञ्चनपुर (34)
Fiscal Year: 076-77
Contract Date: 23-Mar-20
Start Date: 30-Mar-20
Completion Date: 30-Dec-2020 (EOT Done)
Project Description
No description available.