Contract Agreement Amount
Rs. 13,13,84,534
Physical Progress
22.12%
Financial Progress
22.12%
Remaining Payment
Rs. 77
Construction of RCC and Truss (Composite) Bridge Over Rakam Karnali River-Surkhet- Dailekh- Accham Road, Dailekh
Office: सडक डिभिजन, सुर्खेत (33)
Fiscal Year: 067-68
Contract Date: 26-Jul-11
Start Date: 26-Jul-11
Completion Date: 12-Jul-2017 (EOT Done)