Contract Agreement Amount
Rs. 2,91,75,784
Physical Progress
22.00%
Financial Progress
21.93%
Remaining Payment
Rs. 78
Construction of Fulbari Khola Bridge (1*20m) along Tamghas-Simaltari Section of Madan Bhandari Highway, Gulmi District
Office: तम्घास सिमल्टारी प्युठान सडक आयोजना, गुल्मी (180)
Fiscal Year: 078-79
Contract Date: 14-Feb-22
Start Date: 28-Feb-22
Completion Date: 21-Mar-2024 (EOT Done)
Project Description
No description available.