Contract Agreement Amount

Rs. 2,91,75,784

Physical Progress

22.00%

Financial Progress

21.93%

Remaining Payment

Rs. 78

Construction of Fulbari Khola Bridge (1*20m) along Tamghas-Simaltari Section of Madan Bhandari Highway, Gulmi District

Office: तम्घास सिमल्टारी प्युठान सडक आयोजना, गुल्मी (180)

Fiscal Year: 078-79

22.00%

Contract Date: 14-Feb-22

Start Date: 28-Feb-22

Completion Date: 21-Mar-2024 (EOT Done)

Project Description

No description available.