Contract Agreement Amount
Rs. 24,96,53,801
Physical Progress
20.00%
Financial Progress
20.86%
Remaining Payment
Rs. 79
Upgrading Works of Dedhgaun-Dodhbhanjyang-Minamkot-Thapabhanjyang-Dhowadi-Kawasoti Road, Nawalpur
Office: Unknown (55)
Fiscal Year: 078-79
Contract Date: 12-Jul-22
Start Date: 12-Jul-22
Completion Date: 11-Jan-2025 (EOT Not Done)
Project Description
No description available.