Contract Agreement Amount

Rs. 12,46,32,309

Physical Progress

20.54%

Financial Progress

20.45%

Remaining Payment

Rs. 79

Pavement Works Including Cross drainage and Retaining Structures at Inaruwa Na Pa Sakhuwa Gachhi Bata Ramdhuni Na Pa ko Siddhapur Hudai Dakani Than Hudai Ramdhuni Na Pa ko Jhumka Bazar Rajmarg Jodne Jodne Sadak

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 078-79

20.54%

Contract Date: 8-May-22

Start Date: 8-May-22

Completion Date: 13-Apr-2025 (EOT Done)

Project Description

No description available.