Contract Agreement Amount
Rs. 3,39,32,800
Physical Progress
0.00%
Financial Progress
20.36%
Remaining Payment
Rs. 79
Construction of Prestressed RCC Bridge over Sharada Khola, Rapti Rajmarg to Mokhala in Salyan District
Office: सडक डिभिजन, दाङ्ग (31)
Fiscal Year: 073-74
Contract Date: 19-May-17
Start Date: 19-May-17
Completion Date: 16-Feb-2019 (EOT Not Done)
Project Description
No description available.