Contract Agreement Amount
Rs. 54,45,19,893
Physical Progress
21.63%
Financial Progress
19.89%
Remaining Payment
Rs. 80
Construction/Upgrading of Road to blacktop Standard along Pipaltar-Deudi Road(Ch.0+000 - 10+000 km), Nuwakot
Office: Puspalal (Midhill) Road Project, Gorkha (275)
Fiscal Year: 077-78
Contract Date: 4-Feb-21
Start Date: 4-Feb-21
Completion Date: 04-Feb-2023 (EOT Not Done)