Contract Agreement Amount

Rs. 25,40,50,299

Physical Progress

22.00%

Financial Progress

19.85%

Remaining Payment

Rs. 80

M/S Sunkoshi Construction Nepal Pvt.Ltd

Office: योजना तथा अनुगमन महाशाखा (भूवातावरण तथा सामाजिक शाखा) (4)

Fiscal Year: 079-80

22.00%

Contract Date: 6-Feb-23

Start Date: 6-Feb-23

Completion Date: 05-Jun-2025 (EOT Not Done)

Project Description

No description available.