Contract Agreement Amount
Rs. 13,23,34,254
Physical Progress
0.00%
Financial Progress
19.73%
Remaining Payment
Rs. 80
Upgrading works in Lamachaur Dhrachaur - Nepalchaur - Ghari ko pakha Mathillo Fulbari sadak-Bishankhunarayan Road Lalitpur.
Office: मध्यपच्चिमाञ्चल क्षेत्रिय सडक निर्देशनालय,सुर्खेत (10)
Fiscal Year: 079-80
Contract Date: 1-Jan-23
Start Date: 1-Jan-23
Completion Date: 31-Dec-2024 (EOT Not Done)
Project Description
No description available.