Contract Agreement Amount
Rs. 19,27,94,000
Physical Progress
11.00%
Financial Progress
19.72%
Remaining Payment
Rs. 80
Design and Build of Bridge over Bahune Khola, Dhansar Khola, Lukuwa Khola , Kokaha Khola, Phesuwa Khola and Ramguwa Khola Tamor Corridor (Chatara- Mulghat-Subhang Khola ) Road Project
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 077-78
Contract Date: 18-Feb-22
Start Date: 18-Feb-22
Completion Date: 17-Feb-2025 (EOT Not Done)
Project Description
No description available.