Contract Agreement Amount

Rs. 13,52,03,344

Physical Progress

3.37%

Financial Progress

19.51%

Remaining Payment

Rs. 80

Roadway excavation Structure and Gravel works in Bhorle Dahakhani Upradaangadhi Road Chitwan (0+000 to 15+000)

Office: उत्तर दक्षिण, कोशी सडक योजना, संखुवासभा (57)

Fiscal Year: 078-79

3.37%

Contract Date: 12-Jul-22

Start Date: 12-Jul-22

Completion Date: 08-Jul-2024 (EOT Not Done)

Project Description

No description available.