Contract Agreement Amount

Rs. 91,26,403

Physical Progress

19.46%

Financial Progress

19.27%

Remaining Payment

Rs. 80

Pavement Work including Cross drainage and Retaining Structures along Chudamani chowk Jhangar tole Dhanpati tole Bakullachan Madhuwan jane Sadak Kalopattre, Sunsari

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 078-79

19.46%

Contract Date: 3-Jan-22

Start Date: 3-Jan-22

Completion Date: 13-Jan-2023 (EOT Done)

Project Description

No description available.