Contract Agreement Amount

Rs. 3,42,14,592

Physical Progress

45.00%

Financial Progress

18.90%

Remaining Payment

Rs. 81

Extension & Rehabilitation Work on Surkhet- Ranimatta- Dailekh Road (Ch: 0+000 to 0+650 & 2+100-3+000)

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 078-79

45.00%

Contract Date: 28-Oct-21

Start Date: 28-Oct-21

Completion Date: 15-Jul-2023 (EOT Done)

Project Description

No description available.