Contract Agreement Amount

Rs. 71,00,018

Physical Progress

0.00%

Financial Progress

18.72%

Remaining Payment

Rs. 81

Roadway Excavation, Gabion and Stone Soling Work Along Heluwabeshi- Bumlingtar- Budhabare Road Section of Leguwa Tumlingtar Heluwabeshi Bumlingtar Budhabare Solu road Package I (Chainage: 0+000 to 0+700)

Office: डिभिजन सडक कार्यालय, तुम्लीङटार, संखुवासभा (174)

Fiscal Year: 076-77

0.00%

Contract Date: 25-Sep-20

Start Date: 25-Sep-20

Completion Date: 13-Apr-2022 (EOT Done)

Project Description

No description available.