Contract Agreement Amount

Rs. 16,89,51,361

Physical Progress

20.00%

Financial Progress

17.87%

Remaining Payment

Rs. 82

Sanagaun Simaldada Thapagaun Ganjari Pokhari Bagada Gajada Dulbasta hudai Achham Road, Doti

Office: डिभिजन सडक कार्यालय, दोलखा (18)

Fiscal Year: 078-79

20.00%

Contract Date: 18-Feb-22

Start Date: 18-Feb-22

Completion Date: 18-Nov-2024 (EOT Not Done)

Project Description

No description available.