Contract Agreement Amount
Rs. 3,17,64,681
Physical Progress
0.00%
Financial Progress
17.56%
Remaining Payment
Rs. 82
Road Upgrading Works on Thori-Bhandara-Malekhu Sadak(Chepang Marga),Chitwan
Office: डिभिजन सडक कार्यालय, चितवन (20)
Fiscal Year: 076-77
Contract Date: 26-Jun-20
Start Date: 26-Jun-20
Completion Date: 19-Apr-2021 (EOT Not Done)