Contract Agreement Amount

Rs. 25,13,30,350

Physical Progress

24.00%

Financial Progress

17.06%

Remaining Payment

Rs. 82

D & B of kaligandaki River Bridge Andhighat - Bardale Road Syangja

Office: पुल योजना पश्चिम क्षेत्र सेक्टर नंः ४, पाल्पा (221)

Fiscal Year: 074-75

24.00%

Contract Date: 8-Dec-17

Start Date: 8-Dec-17

Completion Date: 06-Dec-2020 (EOT Not Done)

Project Description

No description available.