Contract Agreement Amount

Rs. 66,55,445

Physical Progress

0.00%

Financial Progress

16.60%

Remaining Payment

Rs. 83

Widening and Overlay works (Periodic Maintenance) on Aaptari- Devghat Road

Office: डिभिजन सडक कार्यालय, चितवन (20)

Fiscal Year: 076-77

0.00%

Contract Date: 24-Feb-20

Start Date: 25-Feb-20

Completion Date: 09-Jul-2020 (EOT Not Done)