Contract Agreement Amount

Rs. 39,53,540

Physical Progress

20.00%

Financial Progress

16.53%

Remaining Payment

Rs. 83

Corridor - Dhurpur-Kholete to Talkuna Sadak,Baglung

Office: Road Division, Baglung (254)

Fiscal Year: 076-77

20.00%

Contract Date: 10-Jun-20

Start Date: 10-Jun-20

Completion Date: 15-Dec-2020 (EOT Not Done)

Project Description

No description available.