Contract Agreement Amount
Rs. 64,26,51,161
Physical Progress
16.47%
Financial Progress
16.47%
Remaining Payment
Rs. 83
Construction/Upgrading of Road to blacktop Standard along Pipaltar-Deudi Road(Ch.10+000- 20+872 km), Nuwakot
Office: Puspalal (Midhill) Road Project, Gorkha (275)
Fiscal Year: 077-78
Contract Date: 3-Feb-21
Start Date: 3-Feb-21
Completion Date: 03-Feb-2023 (EOT Not Done)
Project Description
No description available.