Contract Agreement Amount

Rs. 11,67,12,104

Physical Progress

18.00%

Financial Progress

16.46%

Remaining Payment

Rs. 83

Road Improvement Works along Rautahat Chandrapur ward no.8 Santpur Sindhureghari Malintole Chetnagar Samm Pakki Sadak (Ch 0+000 to 20+000), Rautahat (total length of working section : 7:55KM)

Office: पुर्वाञ्चल क्षेत्रिय सडक निर्देशनालय, झापा (7)

Fiscal Year: 079-80

18.00%

Contract Date: 7-Feb-23

Start Date: 7-Feb-23

Completion Date: 03-Feb-2025 (EOT Not Done)

Project Description

No description available.