Contract Agreement Amount

Rs. 61,50,84,417

Physical Progress

54.13%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Construction of Janakpur Dhalkebar Irrigation Canal

Office: Janakpur Parikrama, Byparik Margha Bistaar Yojana (Jatahi-Janakpur), Mahottari (232)

Fiscal Year: 075-76

54.13%

Contract Date: 20-Aug-19

Start Date: 5-Sep-19

Completion Date: 16-Jul-2021 (EOT Done)

Project Description

No description available.