Contract Agreement Amount
Rs. 3,97,26,191
Physical Progress
15.75%
Financial Progress
15.75%
Remaining Payment
Rs. 84
Perodic Maintenance Works on Surkhet-Dailekh Road (Ch.0+000 to 11+000,16+000 to 22+000, 25+000-32+000 & 45+000 to 64+000)
Office: सडक डिभिजन, सुर्खेत (33)
Fiscal Year: 077-78
Contract Date: 29-Mar-21
Start Date: 29-Mar-21
Completion Date: 09-Jul-2021 (EOT Not Done)
Project Description
No description available.