Contract Agreement Amount
Rs. 6,64,36,483
Physical Progress
0.00%
Financial Progress
15.42%
Remaining Payment
Rs. 84
PSC Bridge Over Thambu Khola Dhading
Office: डिभिजन सडक कार्यालय, चितवन (20)
Fiscal Year: 073-74
Contract Date: 13-Jul-17
Start Date: 20-Jul-17
Completion Date: 20-Jul-2019 (EOT Not Done)
Project Description
No description available.