Contract Agreement Amount
Rs. 17,51,27,665
Physical Progress
14.00%
Financial Progress
15.27%
Remaining Payment
Rs. 84
Construction of Blacktop Works on Baruwa Bazar Bairabpur Parsa Chowk Baidar Chirauli Ajingare Sahidpark Gangate, Madi-2, Chitwan
Office: डिभिजन सडक कार्यालय, चितवन (20)
Fiscal Year: 078-79
Contract Date: 8-Jul-22
Start Date: 8-Jul-22
Completion Date: 09-Jul-2023 (EOT Not Done)
Project Description
No description available.