Contract Agreement Amount
Rs. 3,09,47,700
Physical Progress
0.00%
Financial Progress
14.91%
Remaining Payment
Rs. 85
Supplying, Fabricating and Installation of ISMC Steel Channel with GI Railing & Rcc Jersey Barrier works Dhobighat to Kalanki of Kathmandu Ringroa
Office: काठमाडौं चक्रपथ सुधार योजना, ललितपुर (172)
Fiscal Year: 077-78
Contract Date: 9-Sep-21
Start Date: 10-Sep-21
Completion Date: 08-Aug-2022 (EOT Not Done)
Project Description
No description available.