Contract Agreement Amount

Rs. 3,96,33,650

Physical Progress

0.00%

Financial Progress

14.88%

Remaining Payment

Rs. 85

Road Construction(Gravelling) Works on Gadhimai-Kawahigoth (Suwarna Ga.Pa. 7 Santganj Jamuni Solakpur Kawahi) Road, Bara

Office: डिभिजन सडक कार्यालय, मकवानपुर (19)

Fiscal Year: 076-77

0.00%

Contract Date: 13-May-20

Start Date: 13-May-20

Completion Date: 13-Mar-2021 (EOT Not Done)

Project Description

No description available.