Contract Agreement Amount

Rs. 1,23,69,462

Physical Progress

0.00%

Financial Progress

14.77%

Remaining Payment

Rs. 85

Construction of Blacktop Road Works on Bharatpur Mahanagar Ring Road

Office: डिभिजन सडक कार्यालय, चितवन (20)

Fiscal Year: 077-78

0.00%

Contract Date: 21-Jun-21

Start Date: 21-Jun-21

Completion Date: 14-Jan-2023 (EOT Done)

Project Description

No description available.