Contract Agreement Amount

Rs. 3,58,98,01,635

Physical Progress

15.51%

Financial Progress

14.71%

Remaining Payment

Rs. 85

Widening of Sangha-Dhulikhel Section (Asphalt Concrete works) of Suryabinayak Dhulikhel Road Chainage 7+500-15+800)

Office: योजना तथा अनुगमन महाशाखा (योजना अनुगमन तथा मुल्यांकन शाखा) (3)

Fiscal Year: 079-80

15.51%

Contract Date: 13-Dec-22

Start Date: 13-Dec-22

Completion Date: 12-Dec-2025 (EOT Not Done)

Project Description

No description available.