Contract Agreement Amount
Rs. 15,04,79,884
Physical Progress
15.00%
Financial Progress
14.70%
Remaining Payment
Rs. 85
Roadway cutting & structural works on Mangalsen-Suwakhand-Khetgaire-Julumare-Dhakari Road Section
Office: डिभिजन सडक कार्यालय, साँफेवगर, अछाम (178)
Fiscal Year: 078-79
Contract Date: 29-Apr-22
Start Date: 29-Apr-22
Completion Date: 29-Apr-2025 (EOT Not Done)
Project Description
No description available.