Contract Agreement Amount
Rs. 83,54,445
Physical Progress
0.00%
Financial Progress
14.45%
Remaining Payment
Rs. 85
Specific Maintenance (Drain Construction and Maintenance) Works on Chure-Pathlaiya section (East Side) of TRP
Office: डिभिजन सडक कार्यालय, मकवानपुर (19)
Fiscal Year: 076-77
Contract Date: 12-Mar-20
Start Date: 12-Mar-20
Completion Date: 04-Jul-2020 (EOT Not Done)
Project Description
No description available.