Contract Agreement Amount

Rs. 6,82,64,088

Physical Progress

14.20%

Financial Progress

14.28%

Remaining Payment

Rs. 85

Roadway Excavation, Construction of Drain and Structure,Hume Pipe Culverts upto Blacktop standard along Chisapani -Dhakaha-Chakmake-Bahun Tilping -Nawalpurghat-Palapu(59+000 to 69+000)

Office: डिभिजन सडक कार्यालय, खुर्कोट (185)

Fiscal Year: 078-79

14.20%

Contract Date: 7-Mar-22

Start Date: 7-Mar-22

Completion Date: 03-Jul-2024 (EOT Not Done)

Project Description

No description available.