Contract Agreement Amount

Rs. 1,09,52,132

Physical Progress

0.00%

Financial Progress

14.05%

Remaining Payment

Rs. 85

Road Improvement Works at Gadhimai Kawabhighot Sadak,Bara

Office: डिभिजन सडक कार्यालय, मकवानपुर (19)

Fiscal Year: 073-74

0.00%

Contract Date: 6-Feb-18

Start Date: 6-Feb-18

Completion Date: 09-Aug-2019 (EOT Done)

Project Description

No description available.