Contract Agreement Amount
Rs. 4,07,74,459
Physical Progress
15.00%
Financial Progress
13.48%
Remaining Payment
Rs. 86
Pavement and structural works for Rehabilitation of works on Siddhicharan Rajmarg (Mude-Phaplu road section), Solukhumbu
Office: योजना तथा अनुगमन महाशाखा (सडक सुरक्षा तथा ट्राफिक शाखा) (5)
Fiscal Year: 080-81
Contract Date: 15-Sep-23
Start Date: 15-Sep-23
Completion Date: 04-Jul-2024 (EOT Not Done)
Project Description
No description available.