Contract Agreement Amount
Rs. 3,38,71,954
Physical Progress
30.00%
Financial Progress
13.04%
Remaining Payment
Rs. 86
Malika -Sanidev- J.B. J.V.
Office: धनगढी-खुटिया-दिपायल-चैनपुर-उरैभन्ज्याङ्ग सडक योजना, बि.पी. नगर, डाेटी (294)
Fiscal Year: 078-79
Contract Date: 31-Jan-22
Start Date: 13-Feb-22
Completion Date: 06-Jun-2025 (EOT Done)
Project Description
No description available.