Contract Agreement Amount
Rs. 35,17,60,000
Physical Progress
20.00%
Financial Progress
13.02%
Remaining Payment
Rs. 86
Design and Build of Triyuga River Bridge, Hadiya Gabisa haal Chaudandi NaPa 10 antargat Hadiya-Dewdhar Road, Udaypur, Udaypur
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 078-79
Contract Date: 7-Dec-22
Start Date: 7-Dec-22
Completion Date: 03-Jun-2026 (EOT Done)
Project Description
No description available.