Contract Agreement Amount
Rs. 5,30,27,622
Physical Progress
24.90%
Financial Progress
12.96%
Remaining Payment
Rs. 87
Construction of Jallad Khola Multicell Box Culvert along Kadamchowk-Kamla Road
Office: डिभिजन सडक कार्यालय, सिराहा (16)
Fiscal Year: 078-79
Contract Date: 1-Jul-22
Start Date: 1-Jul-22
Completion Date: 31-Jan-2024 (EOT Done)
Project Description
No description available.