Contract Agreement Amount

Rs. 1,02,58,720

Physical Progress

20.00%

Financial Progress

12.90%

Remaining Payment

Rs. 87

Highway Upgrading and Rehabilitation Works along Rapti Highway Shitalpati- Musikot Road (Belatighar to Patare section) in Salyan District.

Office: सडक डिभिजन, दाङ्ग (31)

Fiscal Year: 078-79

20.00%

Contract Date: 25-Nov-21

Start Date: 11-Dec-21

Completion Date: 09-Jun-2022 (EOT Not Done)

Project Description

No description available.